An acceptance sheet with a gas reading but no sample reference leaves the quality team with an immediate question: what was tested? Start the demonstration with an identified drawing and a measurement plan. In the timing notes, distinguish the interval when gas is filling from the time occupied by the complete press sequence.

For an insulating glass line with gas filling, the sample list sets the scope of the demonstration. If the largest pane has been omitted, or a coated construction replaced with clear glass, write that down beside the affected drawing. The factory meeting can then finish with both tested results and a visible list of exceptions.

Turn the Demonstration Into a Sample Schedule

Choose samples from approved drawings, including a regular production size and the largest relevant unit. Each identifier should lead back to the pane sizes, thicknesses, cavities, spacer and coating positions. Where the order includes triple glazing, put its actual construction on the trial schedule. A double unit cannot supply the missing record for the second cavity.

Before the machine starts, decide who is writing the record. Include preparation and any manual help, not just control settings. The person taking measurements and the witness should know what happens if the sample misses a limit. Keep space for the correction and repeat result on the same record.

If a coated sample cannot arrive for the run, keep its drawing on the schedule and mark it untested. Give it a follow-up action. It should still be visible when the buyer returns to the record weeks later.

How to Verify Gas Filling and Pressing on an Insulating Glass Line.png

Separate Gas Filling Time From Complete Cycle Time

Two figures in the Wentrica proposal need careful labels. There is a 7 to 8 second filling reference for 1 square metre of glass, and a stated gas filling rate above 90 percent. The described arrangement fills from the bottom, with gas channels corresponding to glass size. Ask what construction, gas and measurement conditions were used for those figures before putting them into the trial specification.

A filling interval does not tell the buyer when the next finished unit is available. Choose start and finish points for the full sequence, then keep waiting, positioning and handling visible in the timing notes. On the comparison sheet, a figure supplied as filling time should retain that description.

Review the automatic vertical line with a gas-filling press using that distinction. Ask what happens before gas enters, when pressing finishes and when the unit is available to the next station. Request results for the actual sample schedule rather than calculating daily output from the filling interval.

Agree How Concentration Will Be Measured

Choose the concentration instrument with the actual sample construction in front of you. Discuss the coated or multi-cavity sample with the instrument supplier. Its instructions should establish the procedure used. On the trial sheet, record the device and measurement location, when the reading was taken, and the checks made under those instructions.

Sparklike's guide for laser gas measurement explains that coatings and measurement side require attention; its triple-unit procedure also distinguishes cavity results. That is a reason to agree a method with the instrument supplier. It is not evidence that a particular instrument is supplied with the Wentrica line.

A triple-unit report needs to explain its cavity results. If the instrument reports one number, establish what it represents before recording it as acceptance of a two-cavity construction. Where the chosen instrument cannot verify the construction, the measurement method remains an open trial item.

Write the acceptance threshold before taking the reading. The resulting measurement can then be compared with an agreed requirement, with a defined response if it falls short. A reference in a machine proposal should not quietly become a universal certification rule.

Check Alignment With Its Test Condition Attached

For alignment, the relevant footnote is in the technical-data table: plus or minus 0.5 mm was specified with a 1 by 1 m double-glass test. The proposal describes servo positioning and pressing, but the test condition still matters. Carry it into any discussion of that reference result.

Mark the reference edges on the sample drawing and show any intentional offset. Then agree the measurement points. Without that drawing, the inspector may be comparing an intended step with a tolerance meant for aligned edges.

Follow the large triple sample through unloading as well as the press. Identify its construction on the trial sheet and settle any different method or tolerance in advance. The result can then be read against a requirement both parties accepted before the machine ran.

Gas filling openings at the lower edge of the IG press.png

Keep Spacer and Sealing Decisions in the Record

Identify the spacer used in every trial unit. If the planned route includes the automatic flexible spacer applicator, ask whether the demonstration uses that machine or a separately prepared spacer. Write down which arrangement was actually tested.

Agree how units will move to sealing after pressing. Where a single-component hot-melt process is proposed, review the insulating glass hot melt sealing robot as a separate part of the scope. Confirm whether it is present in the acceptance run and which material will be used.

If the sealing machine did not run, its acceptance is still outstanding. Give the press and sealing results their own entries, with any later unit checks attached to the same sample identifier. The record then shows what was actually demonstrated.

Use a Record That Explains the Result

Keep the original measurements even when the unit has to run again. Beside the repeat, explain the correction and the acceptance decision. Someone absent from the demonstration should be able to follow that sequence from the sheet, without asking why the first result disappeared.

Record field

What to enter

Sample identity

Drawing revision, pane stack and spacer

Test conditions

Gas type, settings and defined cycle boundaries

Concentration check

Instrument, method, cavity identification and results

Alignment check

Reference edges, measurement method and results

Intervention

Adjustment, interruption or manual assistance

Decision

Accepted, repeat required or outside approved scope

 

There is a practical data question behind this form: which entries can the controls export? Look at an actual export from the controls and compare it with the trial form. Any missing entries will need a separate record. Where an additional export function is required, get it included in the equipment scope.

Close Failed and Untested Items Before Acceptance

A failed result needs a next action beside its sample identifier. Write down the proposed setting or configuration change, with the person who will carry it out. The failed item remains open while the correction is made and its repeat result is reviewed.

Factory acceptance and site acceptance need separate scopes in the agreement. At the customer's plant, the utilities are those prepared for that installation. Before the technician travels, settle which checks will be repeated there and have the relevant samples ready.

Send the sample schedule to Wentrica through its gas-filling line technical inquiry. Request a trial proposal that names the measurement method, scope and acceptance conditions. That is a more specific starting point than asking whether the machine can fill gas quickly.

Conclusion

A completed record ties a drawing to its settings, measurements and decision. Untested combinations remain on the open list. Use those two documents at acceptance to establish which gas-filling and pressing work has been demonstrated and which work still requires an answer.

FAQ

Q1: Is the quoted filling time the complete production cycle?

The proposal labels its 7 to 8 second figure as filling time for 1 square metre of glass. Keep that description. For capacity discussions, request a timed run from the agreed start point through discharge, using the buyer's sample mix.

Q2: What gas concentration should the buyer accept?

Settle the requirement in the trial specification before taking readings. It needs to suit the ordered construction and relevant quality requirements. The supplier's published filling figure also needs an explanation of how it was measured; it is not a substitute for that agreement.

Q3: Can one gas reading approve a triple-glazed unit?

What does the reading represent? The report needs to answer that for both cavities. Use the instrument supplier's procedure for the pane stack and coatings, with the cavity identification visible next to the drawing.

Q4: Is the gas measurement device included with the production line?

Only the quotation can settle inclusion. If an instrument is being supplied, its model and scope should appear there, along with the arrangements for checks and training. Mentioning a measurement method in a trial discussion does not add equipment to the order.

Q5: What should happen after a failed sample?

Preserve the first result and attach the proposed correction to that sample identifier. A repeat run then has a clear reason and a result to compare. Leave the item open until the responsible people have reviewed the evidence and recorded their decision.

Wentrica
Specializes in providing comprehensive, one-stop solutions for the design, production, and export of equipment in the glass deep processing and door/window industries

QUICK LINKS

CONTACT US
 Tel: +86-185-6282-7317 / +86-156-1595-8376
 E-mail: info@wentrica.com
 Address: Qingda Industrial Area, Chengyang, Qingdao,China
Copyright © 2024 Qingdao Wentrica Composites Co., Ltd All rights reserved Sitemap